Project Overview
An open big-box shell, built as retail, not for public assembly, had to become a single-story convention auditorium — a structural problem before a finish one. In south Houston, Epic ran the entire job: cutting the slab for new plumbing, framing a curved performance stage from radius track, and sequencing every trade from rough-in to closeout. It was Epic’s second engagement in the building, following the framing of its worship space in 2016–17.
Services on This Project
- Location
- Houston, TX
- Timeline
- Aug 2022 – Jan 2024
- Role
- General Contractor
- Existing Building
- Former Kmart
- Facility
- Convention Auditorium
Scope of Work
- Radius-track performance stage, custom-framed on site in the main hall
- Metal stud framing and insulation throughout the auditorium and support spaces
- Drywall installation across the convention hall, corridors, and back-of-house
- Acoustical ceilings, door hardware, fire caulking, and sealant throughout
- Plumbing, tape, float, and paint held under Epic’s contract
- Exterior entry signage at the building’s main campus entrance
Project Photos
Start Your Next Project
Ready to Build?
Tell us what you're building. We'll talk through scope, schedule, and budget, then give you a straight answer on whether Epic is the right contractor for the job.
Get in Touch
+1 (281) 768-4510 info@epiccontractors.comBonded, insured, and ready to talk, whether you're mid-bid or still in pre-construction.
Contact Us →